Sr.No. | Particulars | Maximum Indicative Timelines |
---|---|---|
1. | Initial scrutiny of the claim Application Form | Within 7 days* from the date of claim Application submission. Deficiencies, if any, found in the applications during the scrutiny shall be intimated to the applicants. |
2 | Final scrutiny of claim applicant including site inspection by PMA and recommendation by PMA to DoT | Within 15 days* from the last date of rectification in deficiency in claim Application Form. |
3 | Final approval of claim amount and release of incentive by DoT | Within 23 days from the date of final recommendation by PMA to DoT. |
Note:
Overall time taken by PMA for initial scrutiny of claim application (S.No.1) and recommendation (S.No.3) should be undertaken within the overall timeline of 22 days. |